Greenway Project Updates: May 2017

Progress continues on 6.8 miles of new greenway under construction across the region

Despite the recent rainy weather, progress continues on 6.8 miles of new greenway under construction across the region!

In St. Charles County, work is underway on the Centennial Greenway expansion over Highways 364 and 94.  The route has been cleared and contractors have started driving steel pile into the bedrock to support the new bicycle and pedestrian bridges, which are slated to be installed over the highways this September.

Along the Fee Fee Greenway in Maryland Heights, contractors are focused on excavation and earthwork to prepare the way for the new connection that will link Aquaport and McKelvey Woods to Creve Coeur County Park.

In south St. Louis County, work continues in the Mississippi Greenway: Cliff Cave Park where contractors are building the abutments for the walking and biking bridge over Cliff Cave Road. They are also building new retaining walls and working on the new stretch of greenway that will connect the upper and lower sections of the park.

On the north end of the River des Peres Greenway, contractors have already finished several segments of the new greenway and are rebuilding  portions of the roadway on Ellendale. You can also see the greenway taking shape on the Lansdowne bridge where it will connect to the Shrewsbury MetroLink Station.

On the south end of River des Peres Greenway, the extension from Alabama to Broadway through Lemay Park is almost finished and is open to cyclists, joggers and walkers. The segment that will eventually connect with the Mississippi Greenway near the River City Casino has temporarily been put on hold.  We are working with our partners at Metropolitan St. Louis Sewer District to coordinate some planned repairs to the banks of the River des Peres as well as some sewer line improvements. As stewards of taxpayer funds, we do not want to build this segment of greenway only to tear it up again in the coming months to accommodate this construction. We will let you know the updated timeline for completing the connection as soon as details are finalized. Thank you for your patience!